Time taken by Rahul to complete work alone
CAT 2021 Slot 3 · QA · Easy · Work and time
One day, Rahul started a work at 9 AM and Gautam joined him two hours later. They then worked together and completed the work at 5 PM the same day. If both had started at 9 AM and worked together, the work would have been completed 30 minutes earlier. Working alone, the time Rahul would have taken, in hours, to complete the work is
- A.
12
- B.
11.5
- C.
12.5
- D.
10
D
Explanation
Let Rahul's rate of work be per hour and Gautam's rate be per hour.
In the first case, Rahul works from 9 AM to 5 PM (8 hours) and Gautam works from 11 AM to 5 PM (6 hours): --(1)
In the second case, both work together from 9 AM for 7.5 hours (30 minutes earlier than 5 PM): --(2)
Subtracting (2) from (1):
So Rahul alone would take hours to complete the work.