Time taken by L alone
CMAT 2021 · QTDI · Easy · Time and Work
L and M together can complete a piece of work in 72 days, M and N together can complete it in 120 days, and L and N together in 90 days. In what time can L alone complete the work?
- A.
150 days
- B.
80 days
- C.
100 days
- D.
120 days