Time and Work - Cans Preparation
CAT 1998 Slot 1 · QA · Easy · Arithmetic
A company has a job to prepare certain number cans and there are three machines A, B and C for this job. A can complete the job in 3 days, B can complete the job in 4 days, and C can complete the job in 6 days. How many days will the company take to complete the job if all the machines are used simultaneously?
- A.
4 days
- B.
4/3 days
- C.
3 days
- D.
12 days
Answer
B
Explanation
In 1 day, A does , B does , and C does of the work.
Together in 1 day, they do of the work.
Hence, time taken days.