Men and Machine Efficiency Comparison
CAT 2019 Slot 1 · Quantitative Ability · Medium · Work, time
This is a medium Quantitative Ability question from the CAT 2019 Slot 1 paper. It tests Work, time. The full answer key and a step-by-step explanation are below — try it yourself first, then reveal the solution.
Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?
13
Explanation
Let efficiency of 1 man be and 1 machine be . . Two machines do the work in 13 days . Number of men needed to finish in 13 days .
Related Work, time questions
- #393Work and Time with Varied EfficienciesCATQAMCQMedium
- #409Product of Distinct Roots of Absolute QuadraticCATQAMCQMedium
- #410Bicycle Wheel Revolutions and SpeedCATQAMCQMedium
- #411Exponential Function Equation and SummationCATQATITAMedium
- #412Exam Averages and Individual Score CalculationCATQAMCQMedium
- #459Ratio of speeds of carsCATQAMCQMedium
- #460Largest possible value of first termCATQAMCQHard
- #461Paint mixture ratio in drum 2CATQAMCQMedium
Practise this under exam conditions
Sign in to solve it with a live timer, the on-screen CAT calculator, and streak and accuracy tracking across every question you attempt.
Solve in the workspace