Decision Making: PERT/CPM Project Management in Kitchen
XAT 2023 · DM · Hard · Operations
Passage / data set
Go through the following scenario and answer the THREE questions that follow.
To prepare a dish (e.g., Dosa- Sambhar, Idli-chutney, Rajma-Chawal, Mawa-Bati), the chef has to finish nine activities, some of which could be done simultaneously, while others could not be done simultaneously. One of the challenges faced by the chef was to precisely calculate the preparation time of a dish and communicate the waiting time to the customers.
However, based on the past data, the chef had an idea about approximate time taken to complete each activity. He had noted down the best (optimistic), worst (pessimistic) and most likely (most commonly observed) time to finish each of the nine activities. Further, the chef realised that frequency of occurrence of most likely time was 66.666%, and the frequency of occurrence of pessimistic and optimistic times were 16.666% each. The table shows the optimistic, pessimistic, and most likely times for each activity. Time is indicated in minutes in the table below.
Dependencies: A is initial; B and C start after A. D, F, G depend on B. E and H depend on C. I depends on all.
| Activity | Optimistic (16.666%) | Pessimistic (16.666%) | Most Likely (66.666%) |
|---|---|---|---|
| A | 1 | 1 | 1 |
| B | 2 | 3 | 3 |
| C | 10 | 13 | 12 |
| D | 5 | 5 | 5 |
| E | 3 | 6 | 4 |
| F | 1 | 1 | 1 |
| G | 5 | 10 | 7 |
| H | 9 | 13 | 10 |
| I | 5 | 5 | 5 |
Question 1 of 3
The expected time to prepare the dish is the weighted average of optimistic, pessimistic and most likely time. Which of the following is the expected wait time for the chef to communicate to the customers?
- A.
Approx. 22.0
- B.
Approx. 51.0
- C.
Approx. 47.3
- D.
Approx. 32.3
- E.
Approx. 40.0
Question 2 of 3
Customer dissatisfaction is the difference of actual waiting time (AWT) and expected waiting time (EWT). AWT is the actual time spent by customer before being served the dish. EWT of the customer is the time communicated by the chef. What is the minimum waiting time (EWT) that the chef should communicate to minimise customer dissatisfaction?
- A.
38
- B.
33
- C.
40
- D.
42
- E.
35
Question 3 of 3
Which of the following is the MOST volatile activity for the chef?
- A.
G
- B.
B
- C.
C
- D.
H
- E.
E
Practise this under exam conditions
Sign in to solve it with a live timer, the on-screen CAT calculator, and streak and accuracy tracking across every question you attempt.
Solve in the workspace