Time required for Ganesh to complete work alone
CAT 2018 Slot 2 · Quantitative Ability · Medium · Time & Work
This is a medium Quantitative Ability question from the CAT 2018 Slot 2 paper. It tests Time & Work. The full answer key and a step-by-step explanation are below — try it yourself first, then reveal the solution.
Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?
- A.
12
- B.
14.5
- C.
13.5
- D.
11
C
Explanation
Let daily work of Ramesh be and Ganesh be . Total work .
Work remaining after 7 days . For the next 10 days (total 17 days), Ramesh works at and Ganesh at . So:
Work remaining after 7 days .
If Ganesh works alone after Ramesh gets sick, time taken by Ganesh .
Related Time & Work questions
- #479Time to fill tank using both pumpsCATQAMCQMedium
- #481Largest possible value of linear expressionCATQATITAHard
- #482Ratio of new score to original scoreCATQAMCQMedium
- #483Shortest distance from originCATQAMCQMedium
- #484Count of two-digit numbersCATQAMCQMedium
- #485Time to fill tank with two types of inletsCATQATITAMedium
- #486Sum of principal amountsCATQATITAMedium
- #487Minimum possible value of xCATQATITAHard
Practise this under exam conditions
Sign in to solve it with a live timer, the on-screen CAT calculator, and streak and accuracy tracking across every question you attempt.
Solve in the workspace