Road construction workforce
CAT 2020 Slot 3 · QA · Easy · Time and work
A contractor agreed to construct a road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?
Answer
40
Explanation
Work done in 60 days by 140 persons = . Remaining work = . Remaining time = days.
Using : .
Additional people needed = .