Road construction workforce
CAT 2020 Slot 3 · Quantitative Ability · Easy · Time and work
This is an easy Quantitative Ability question from the CAT 2020 Slot 3 paper. It tests Time and work. The full answer key and a step-by-step explanation are below — try it yourself first, then reveal the solution.
A contractor agreed to construct a road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?
40
Explanation
Work done in 60 days by 140 persons = . Remaining work = . Remaining time = days.
Using : .
Additional people needed = .
Related Time and work questions
- #226Area enclosed by lines and axesCATQAMCQMedium
- #227Age ratio problemCATQATITAEasy
- #228Integers not divisible by 2, 5, or 7CATQAMCQHard
- #229Examination marks calculationCATQAMCQEasy
- #230Functional equation evaluationCATQAMCQMedium
- #231Simplify logarithmic fractionCATQATITAMedium
- #232Exponents and powers relationCATQATITAHard
- #233Natural numbers bounded fractionsCATQAMCQHard
Practise this under exam conditions
Sign in to solve it with a live timer, the on-screen CAT calculator, and streak and accuracy tracking across every question you attempt.
Solve in the workspace