Alternate Working Days Completion Time
CAT 2021 Slot 2 · Quantitative Ability · Medium · Rates & Work
This is a medium Quantitative Ability question from the CAT 2021 Slot 2 paper. It tests Rates & Work. The full answer key and a step-by-step explanation are below — try it yourself first, then reveal the solution.
Anu, Vinu and Manu can complete a work alone in 15 days, 12 days and 20 days, respectively. Vinu works everyday. Anu works only on alternate days starting from the first day while Manu works only on alternate days starting from the second day. Then, the number of days needed to complete the work is
- A.
8
- B.
6
- C.
5
- D.
7
D
Explanation
Let total work be units. Daily work rates:
- Anu units/day
- Vinu units/day
- Manu units/day
Work done on odd days (Vinu + Anu) units. Work done on even days (Vinu + Manu) units.
In a 2-day cycle, work done units. After 3 full cycles (6 days), work done units. Remaining work units.
On the 7th day (odd day), Vinu + Anu work and produce 9 units, which completes the remaining work. Total days needed days.
Related Rates & Work questions
- #175Time and Work Pairwise CompletionCATQATITAMedium
- #183Three-Digit Numbers Increasing on ReversalCATQATITAHard
- #184Two Trains Crossing Each OtherCATQAMCQMedium
- #185Periodic Recurrence RelationCATQAMCQMedium
- #222Value of x100 in recursive sequenceCATQAMCQMedium
- #223Distinct values of NCATQATITAEasy
- #224Logarithmic identity calculationCATQAMCQHard
- #1291Painting work and share of paymentCATQAMCQEasy
Practise this under exam conditions
Sign in to solve it with a live timer, the on-screen CAT calculator, and streak and accuracy tracking across every question you attempt.
Solve in the workspace