Project Management and Finance Statements
CMAT 2023 · Innovation & Entrepreneurship · Medium · Innovation & Entrepreneurship
Which of the following statement(s) is/are true?
A. Technical feasibility is not required in case of hospital projects. B. Pattern of financing is ignored while computing cost of capital. C. CPM is superior to PERT in some situations. D. Infrastructure projects are ideally financed through long term sources. E. Cost of internally generated funds is zero.
Choose the correct answer from the options given below:
- A.
B, E only
- B.
D and E only
- C.
A and B only
- D.
C and D only
Answer
D
Explanation
- Statement C is true: Critical Path Method (CPM) is superior for deterministic, well-defined projects (like construction), whereas PERT is suited for probabilistic R&D projects.
- Statement D is true: Infrastructure projects require heavy capital expenditure with long gestation periods, so long-term financing is ideal.
- Statement A is false (technical feasibility is mandatory for hospital projects).
- Statement B is false (capital structure impacts overall cost of capital).
- Statement E is false (internally generated funds have an opportunity cost).
Thus, C and D only are correct.
Related Innovation & Entrepreneurship questions
- #3129Business Growth ConcernsCMATINEMCQEasy
- #3130Types of Entrepreneurs: Resistance to ChangeCMATINEMCQEasy
- #3131Bringing Ideas to MarketCMATINEMCQMedium
- #3132Business Plan: Projected GrowthCMATINEMCQEasy
- #3133Entrepreneurial Risk & UncertaintyCMATINEMCQEasy
- #3134Market Feasibility Analysis PriorityCMATINEMCQMedium
- #3135Gary Hamel's Four Pillars of ValueCMATINEMCQMedium
- #3136Types of Innovation: Premium MarketCMATINEMCQEasy
Practise this under exam conditions
Sign in to solve it with a live timer, the on-screen CAT calculator, and streak and accuracy tracking across every question you attempt.
Solve in the workspace