Project Management and Finance Statements
CMAT 2023 · INE · Medium · Innovation & Entrepreneurship
Which of the following statement(s) is/are true?
A. Technical feasibility is not required in case of hospital projects. B. Pattern of financing is ignored while computing cost of capital. C. CPM is superior to PERT in some situations. D. Infrastructure projects are ideally financed through long term sources. E. Cost of internally generated funds is zero.
Choose the correct answer from the options given below:
- A.
B, E only
- B.
D and E only
- C.
A and B only
- D.
C and D only